New Video From The Concrete Foundations of Trilogy’s East Tower
15:12 - 11 Νοεμβρίου 2019

The concrete foundations of Trilogy’s East Tower have been poured just one month after the West Tower’s.
East Tower Concrete Foundations in numbers:
20 hours
130 workers
2,500m3 of concrete
700 tonnes of reinforcement
8 layers